Sample Projects
-

Bioscrip Inc. IT Headquarters
Location: Eden Prairie, MN
Client: Bioscrip
Size: 3,000 SF
Details: New construction including service entrance, generator, UPS system, under-floor circuitry and connections to racks/servers, FM200 system, EPO system and general fire alarm. -

Cargill Data Center
Location: Minnetonka, MN
Client: Cargill
Size: 11,000 SF
Details: New data center including primary service entrance, generator system, UPS systems, redundant PDU systems, redundant PDU whips to racks/servers, FM 200 suppression system, EPO system, VESDA monitor, general fire alarm. -

Cima Labs
Location: Brooklyn Park, MN
Client: KM Building Company
Size: 19,000 SF
Details: New office space and laboratory remodel. -

E-funds
Location: Woodbury, MN
Client: Bainey
Size: 80,000 SF
Details: Construction of call center, data center and offices. -

Gourmet Award Foods Data Center
Location: Minneapolis, MN
Client: Gourmet Award Foods
Size: 1,500 SF
Details: New construction including service entrance, UPS system, redundant PDUs, PDU whip installation to racks/servers, pre-action fire suppression system, EPO system and general fire alarm. -

Hennepin County Data Center
Location: Minneapolis, MN
Client: Hennepin County, MN
Size: 15,000 SF
Details: Remodel of operating data center including installation of generators, electrical service, redundant UPS systems, redundant PDU systems, redundant PDU whips to racks/servers, FM200 suppression system, EPO system, VESDA monitoring system and fire alarm systems. -

Kroll Ontrack
Location: Eden Prairie, MN
Client: Bainey Group
Size: 70,000 SF
Details: New construction including redundant primary utility services and substations, generator system, redundant UPS systems, redundant PDU systems, redundant PDU whips to racks/servers, FM 200 suppression system, EPO system, VESDA monitoring system, general fire alarm, data backbone and horizontal cabling. -

Plum Point Energy Station
Location: Osceola, AR
Client: Superior Building Systems
Size: 53,000 SF
Details: Installation of branch power, lighting, paging system, and phone/data for six support buildings at the Plum Point Coal Fired Generation Plant. Also made 1900 fiber connections and tested 925 strands throughout the entire plant. -

Protein Design Labs
Location: Plymouth, MN
Client: Westin Construction
Size: 30,000 SF
Details: Renovation of manufacturing facility for humanized antibodies. -

U of M Cargill Building for Microbial and Plant Genomics
Location: St. Paul, MN
Client: Shaw-Lundquist
Size: 64,000 SF
Details: Laboratories with open layouts, microbial and plant growing areas, a robotic center for screening new biological compounds, teaching space and offices. -

U of MN Cancer Center
Location: Minneapolis, MN
Client: Sheehy Construction
Size: 160,000 SF
Details: Remodel of three floors as well as addition of four floors, testing labs, office space and penthouse, . -

US Bank Eau Claire Data Center
Location: Eau Claire, WI
Client: US Bank
Size: 1,000 SF
Details: New construction including service entrance, UPS systems, distribution panels, under-floor circuitry to racks/servers, clean agent fire suppression system, EPO system, and general fire alarm. -

Washington County Disaster Recovery Data Center
Location: Washington County, MN
Client: Frerichs
Size: 3,000 SF
Details: Build-out of existing data center.